Deadlines are rarely given as dates. A contract says "within 30 days", an invoice is due "net 60", a notice period is "three months", a supplier promises delivery in "ten working days". Converting those into an actual calendar date sounds trivial until you hit the end of a month, a leap year or a weekend in the middle of the count.
This guide explains how date arithmetic works in practice, including the rules for adding months, how business days are counted, and what ISO week numbers mean. The examples use real 2026 dates so you can check them against a calendar.
Adding days and weeks
Days and weeks are the easy part, because every day is the same length. A week is always seven days, so "6 weeks" is simply 42 days.
Example: 90 days after Thursday 1 October 2026 is Wednesday 30 December 2026.
To count by hand you would work month by month: 30 days remain in October after the 1st, November has 30, so by 30 November you have used 60 days; the remaining 30 land on 30 December.
Adding months and years: the month-end problem
Months have 28, 29, 30 or 31 days, so "one month later" is not a fixed number of days. The usual rule is to keep the same day number in the target month and, if that day does not exist, use the last day of that month.
- 15 January + 1 month = 15 February
- 31 January 2026 + 1 month = 28 February 2026 (there is no 30 or 31 February)
- 31 August + 1 month = 30 September
- 29 February 2028 + 1 year = 28 February 2029
Some software handles this differently. A plain JavaScript date, for example, rolls 31 January + 1 month over to 3 March, because it adds the three "missing" days to February. That is rarely what a contract means, which is why the clamping rule is the common convention.
Month arithmetic is not reversible
Because of clamping, adding and then subtracting a month can land you somewhere different:
- 31 March − 1 month = 28 February
- 28 February + 1 month = 28 March, not 31 March
Order matters when combining units
When adding years, months and days together, the usual order is years first, then months, then days. Take 30 January 2026 + 1 month + 1 day:
- Months first: 30 January + 1 month = 28 February (clamped), + 1 day = 1 March.
- Day first: 30 January + 1 day = 31 January, + 1 month = 28 February.
The two orders differ by a day, which is why a tool should apply a consistent rule, and why contract wording matters.
Business days
Business (working) days usually mean Monday to Friday. To add business days, step forward one day at a time and only count weekdays.
Example: 10 business days after Thursday 1 October 2026.
- The start date itself is not counted.
- Friday 2 October is day 1; the weekend is skipped; Monday 5 to Friday 9 October are days 2 to 6; the next weekend is skipped; Monday 12 to Thursday 15 are days 7 to 10.
- Result: Thursday 15 October 2026, which is 14 calendar days later, with 4 weekend days skipped.
Public holidays
Holidays differ by country, region and even employer, so general-purpose calculators, including ours, skip only Saturdays and Sundays. For each public holiday that falls within the period, add one more business day.
ISO week numbers and day of year
Many businesses, especially in Europe and Asia, plan by week number. Under ISO 8601:
- Weeks start on Monday.
- Week 1 is the week containing the year's first Thursday.
- A year has 52 or 53 weeks.
The rule means the first days of January can belong to the previous year's final week. Friday 1 January 2027, for example, is in week 53 of 2026. Meanwhile, 29 September 2026 is in ISO week 40 and is day 272 of the year.
Calculate dates with our tool
The Date Calculator applies all of these rules and runs in your browser.
- Open the Date Calculator and choose a Start date, or click Today.
- Select Add (+) or Subtract (−).
- Enter any combination of Years, Months, Weeks and Days. For working days, turn on Business days only and enter the number of Business days.
- Read the resulting Date, Day of week, ISO format, ISO week / day of year and Calendar days from start. In business mode you also see Weekend days skipped. If a month-end date was clamped, the tool says so.
- Click Copy date to paste the result into an email, contract or calendar.
Other ways to do date arithmetic
Spreadsheets
Spreadsheets store dates as numbers, so =A2+90 adds 90 days. For months, =EDATE(A2, 1) follows the month-end clamping rule. For working days, =WORKDAY(A2, 10) skips weekends and can take a list of holidays as a third argument, which makes it the better tool when you have a fixed holiday calendar.
Calendar apps
Most calendar apps can show week numbers and let you jump forward by weeks or months. They are fine for quick checks but awkward for "147 days from now".
Code
Date libraries in most programming languages provide month addition with clamping. Plain arithmetic on timestamps (adding 86,400 seconds per day) can go wrong across daylight saving changes, so use date-aware functions.
Pitfalls to avoid
Counting the start day
"Within 10 days of 1 October" is usually read as ending on 11 October, not 10 October, because the start day is not counted. Legal and contractual rules can differ, so check the wording.
Treating "a month" as 30 days
Thirty days after 31 January is 2 March, but one month after 31 January is 28 February. They are different questions.
Forgetting leap years
2028 is a leap year, so any count across February 2028 includes 29 February. A proper date tool handles this automatically.
Measuring rather than adding
To find how many days lie between two dates, use the Date Difference Calculator instead. For ages, the Age Calculator is more convenient, and for events across countries the Time Zone Converter helps with local times.
Frequently asked questions
What date is 90 days from today?
Leave the start date as today, choose Add and enter 90 in Days. The result shows the date and weekday instantly.
What happens when I add a month to 31 January?
The date moves to the last day of February: 28 February, or 29 February in a leap year. The calculator tells you when it has clamped a date.
Does business-day mode skip public holidays?
No. It skips Saturdays and Sundays only, because holidays vary by country and organisation. Add one extra business day for each holiday in the period.
What is an ISO week number?
It is the week number under ISO 8601, where weeks start on Monday and week 1 contains the first Thursday of the year. Dates in early January can belong to the previous year's last week.
How do I count the days between two dates?
This tool adds or subtracts time from a single date. Use the Date Difference Calculator to count the days between two dates.